Category: Notices on Auctions

Nemo Link Announce NEW Summer 2025 Seasonal Product

< Back to index

Nemo Link updates its dynamic overload facility hours

< Back to index

From tomorrow, 17 April 2024, Nemo Link will move its dynamic overload facility which is current running each day between 17:00 – 22:00 CE(S)T to new timings between 10:00 – 15:00 CE(S)T.

This means the Maximum Physical Transfer Capacity (MPTC) of the interconnector at mid-channel reference point will be 1032MW for a period of 5 hours each day between 10:00-15:00 CE(S)T and please note this is only available in the direction BE to GB.

Subject to the day ahead capacity calculation process, market participants will see Nemo Link’s unrestricted Day Ahead Net Transfer Capacity (NTC) of 1032MW (BE to GB direction) between 10:00-15:00 CE(S)T in the day ahead auction on 16 April 2024 for delivery on 17 April 2024.

Any unallocated capacity will flow through to intraday auctions, subject to a further intraday capacity calculation process.

 

Effective from delivery 17/04/2024 until further notice

Background information:

The design of the interconnector means that Nemo Link has the ability to operate the interconnector for short periods (e.g. 5 hours) in excess of its nominal continuous rating by taking advantage of the thermal characteristics of the plant and the in-built redundancy of the cooling systems. Increasing the flow of the interconnector by 20MW is therefore possible for a few hours. This has been introduced on Nemo Link since 18th December 2019.

 

If you have any questions or need any further information, please don’t hesitate to contact the Customer Team.

NEW CAL24 and CAL25 auctions added!

< Back to index

Nemo Link is delighted to announce additional CAL25 and CAL24 Auctions taking place next week with 50MW expected to be offered in each direction in both auctions.

Details of the NEW auctions are as below: 

CAL 2025 (X) 

Auction Details:

NLL-BE-GB-Y-BASE—250101-10

NLL-GB-BE-Y-BASE—250101-10

Auction timings: 
Opening at 14:00 CET Monday 11 December  
Closing at 14:00 CET Tuesday 12 December 

Confirmed ATC Volumes: 
GB-BE 50MW 
BE-GB 50MW  

 

CAL 2024 (VIII)

Auction Details:

NLL-BE-GB-Y-BASE—240101-08

NLL-GB-BE-Y-BASE—240101-08

Auction timings: 
Opening at 14:00 CET Wednesday 13 December  
Closing at 14:00 CET Thursday 14 December 

Confirmed ATC Volumes: 
GB-BE 50MW 
BE-GB 50MW  

 

Auction Calendar: 

An updated Nemo Link 2023 Auction Calendar can be found here. 

Should you have any questions or need further information, please contact the Nemo Link Customer Team.  

 

Nemo Link announces first Y+2 product – CAL 2025 auction

< Back to index

Upcoming CAL2022 on GB-BE border_10 & 11 May

< Back to index

Nemo Link is pleased to announce the upcoming annual capacity auction for Calendar 2022 on 10th and 11th May 2021 on the JAO’s eCAT platform.

This auction will replace the CAL 2022 auction that was planned on 1st and 2nd June 2021.

Please note the information below in preparation for the GB <->BE CAL 2022 auction.

Auction 
Auction Opening
Auction Closing  
Direction
ATC Volumes
CAL 2022 (V)
12:00 CEST 10 May 2021
12:00 CEST 11 May 2021
Both
175 MW

Planned Outage:

Nemo Link published its planned maintenance period for 2022 as follows:

Start Time
Start Date
End Time 
End Date
Interconnector Capacity
07:00 (CEST)
19/09/2022
23:00 (CEST)
25/09/2022
0 MW

All Nemo Link’s planned maintenance schedules can be found on the Maintenance Programme Publications.

Loss Factor:

Please note that the Nemo Link Mid-point loss factor is 2.372%.

Collateral in place:

Please note that in order to be able to place bids in the annual auction, market participants are required to have in place collateral amounting to 1/12 of the highest value of bids (price x volume) entered for the annual product. Further information on credit calculation can be found in JAO’s Information System Rules (appendix 6, 7 & 8).

Should you have any questions or need further information, please contact the Nemo Link Customer Team.

 

1st CAL2022 on GB-BE border

< Back to index

Nemo Link is pleased to announce its 1st CAL2022 auction on the GB-BE border on 1st and 2nd March 2021 on the JAO’s eCAT platform.

Please note the information below in preparation for the CAL 2022 auction.

Auction 
Auction Opening
Auction Closing  
Direction
ATC Volumes
CAL 2022 (I)
12:00 CET 1 Mar 2021
12:00 CET 2 Mar 2021
Both
175 MW

Planned Outage:

Nemo Link published its planned maintenance period for 2022 as follows:

Start Time
Start Date
End Time 
End Date
Interconnector Capacity
07:00 (CEST)
19/09/2022
23:00 (CEST)
25/09/2022
0 MW

All Nemo Link’s planned maintenance schedules can be found on the Maintenance Programme Publications.

Loss Factor:

Please note that the Nemo Link Mid-point loss factor is 2.372%.

Collateral in place:

Please note that in order to be able to place bids in the annual auction, market participants are required to have in place collateral amounting to 1/12 of the highest value of bids (price x volume) entered for the annual product. Further information on credit calculation can be found in JAO’s Information System Rules (appendix 6, 7 & 8).

Should you have any questions or need further information, please contact the Nemo Link Customer Team.

 

1st CAL2021 annual auction on the GB-BE border

< Back to index

Nemo Link will be holding its first annual auction capacity in both directions for calendar year 2021 on 7th and 8th September 2020 on the eCAT Auction Platform from the Joint Allocation Office.

Below you can find key information that may be helpful in preparation for the auction.

Physical firmness:

We would like to confirm that in the event of an unplanned outage on the Nemo Link Interconnector, the final nominations (nominated capacity for which the final nomination gate and Day-ahead firmness deadline has passed) will continue to be treated as physically firm.

Offered Capacity:

GB-BE
BE-GB
100 MW
100 MW

Auction Window:

Auction start time
Auction end time
07/09/2020 12:00 CEST
08/09/2020 12:00 CEST

Planned Outage:

Nemo Link published its planned maintenance period for 2021 as follows:

Start Time
Start Date
End Time 
End Date
Interconnector Capacity
07:00 (CEST)
20/09/2021
23:00 (CEST)
26/09/2021
0 MW

All Nemo Link’s planned maintenance schedules can be found on the Maintenance Programme Publications area on our website.

Loss Factor:

Please note that the new Nemo Link Mid-point loss factor is now 2.372% (previously as 2.6% prior to 01/09/2020 ).

Collateral in place:

Please note that in order to be able to place bids in the annual auction, market participants are required to have in place collateral amounting to 1/12 of the highest value of bids (price x volume) entered for the annual product.

Further information on credit calculation can be found in JAO’s Information System Rules (appendix 6, 7 & 8).

 

If you have any questions, please contact the Customer Team.

Get ready for Nemo Link Cal 2020 Auction

< Back to index

Nemo Link will be holding its first ever auction for an annual capacity product in both directions for calendar year 2020 on 2nd and 3rd December 2019 on the Joint Allocation Platform.

Please note that all JAO’s registered participants are entitled to bid in this auction. Below you can find key information that may be helpful in preparation for the auction.

Auction Window:

Auction start time: 02/12/2019 12:15 CET
Auction end time: 03/12/2019 12:15 CET

Planned Outage:

Nemo Link published its planned maintenance period for 2020 as follows:

Start Time
07:00 (CEST)
Start Date
21/09/2020
End Time
23:00 (CEST)
End Date
2/10/2020
Interconnector Capacity
0 MW

All Nemo Link’s planned maintenance programmes can be found on the Maintenance Programme Publications area on our website.

Collateral in place:

Please note that in order to be able to place bids in the annual auction, market participants are required to have in place collateral amounting to 2/12 of the highest value of bids (price x volume) entered for the annual product.

Below is the potential liabilities formula that JAO will use to calculate collateral requirements:

Further information on credit calculation can be found in JAO’s Information System Rules (appendix 6, 7 & 8).

If you have any questions, please contact the Customer Team.

Nemo Link’s first intraday auctions start tomorrow

< Back to index

The first intraday auctions on Nemo Link start tomorrow.  Market Participants will have the option to use hourly nomination gates to optimise their positions – a first for a Channel interconnector.

Following helpful questions from our recent intraday workshop, further details on auction and nomination gates, treatment of losses, rounding, and outage communications can be found here.

The first intraday auction will be held tomorrow on the JAO’s eCAT platform between 09:30 and 09:55 CET. Below is a snap shot of all intraday auctions taking place tomorrow:

Date Auction Time (CET) Delivery period (CET)
14th November 2019 09:30 – 09:55 12:00 – 18:00 14th November 2019
14th November 2019 15:30 – 15:55 18:00 – 24:00 14th November 2019
14th November 2019 21:45 – 22:10 00:00 – 06:00 15th November 2019

From 15th November 2019, auctions will be held according to our Intraday Auction Schedule.

 

Contact Us

Please get in touch if you would like to explore trading opportunities or discuss any matters related to Nemo Link.

Customer Engagement Partner, Michele Jordan
Correspondence Address Nemo Link Limited, Rue Joseph Stevens 7, 1000 BRUSSELS, Belgium

What are you looking for?

Please enter your details

By entering your details you’re subscribing to NemoLink for auction alerts or latest news from our newsletter. We will send you this information by email. You can unsubscribe at any time. Privacy policy